Draft 4.0 8/10/00

 


Testing procedures for SCT modules

Contents

1. Introduction

2. Testing sequence

2.1 Component tests

2.1.1 Introduction

2.1.2 Reception of parts

2.1.3 Bare Hybrid tests

2.1.4 Stuffed hybrid tests

2.1.5 Asic mounted hybrid tests

2.1.6 Detector tests

2.1.7 Fan in tests

2.2 Sub assembly tests

2.3 Module tests

2.4 Tests after shipping

3. Batch tests

3.1 Hybrids

3.2 Detectors

3.3 Detector test structures

4. Standard testing conditions

4.1 Chip tests

4.1.1 Check of hybrid supply currents

4.1.2 Hybrid temperature cycling

4.1.3 Burn in

4.1.4 Test vectors: Simple

4.1.5 Test vectors: Full

4.1.6 Test vectors: Data run

4.2 Detector tests

see: 'ATLAS SCT Detector QA procedures'

4.4 Fan-in tests

5. Database entries and criteria

see (WWW edition, Uni.Geneva): http://polux0.unige.ch/sctprd/doc/userguide/welcome.html

and (PC/Mac version, Uni Manchester): http://hepwww.ph.man.ac.uk/groups/atlas/SCTdatabase/Database.html

6. Infrastructure requirements

 


1. Introduction

This document is a 'living document', liable to be updated at any time. It has grown initially from a series of presentations and discussions in the CERN GENEVA cluster which were then presented in the June 98 SCT week. Following the suggestions then given, each cluster rep. nominated a testing representative. In its present form it owes more to the efforts of the people who prepared QA documents in the UK and the many suggestions from testing representatives in each cluster. These people are consulted before each release of the document, and continue to contribute to the detailed procedures described here.

Suggestions should be sent to me, shaun.roe@cern.ch

After each preliminary circulation of the document to these people (and absorbing their comments), it is posted here for wider comment by the sct community.

 

The document is divided into six parts:
1) An introduction

2) A section giving overall testing procedure seen as a sequence, with cursory explanations of the tests and their aims. Web links to detailed explanations of section 3.

3) Batch tests, to be performed on a subset associated with production

4) Detailed specifications of the tests, with reference to other documents where appropriate, and a description of the likely equipment and manpower needed.

5) A list of variables extracted from the tests, with pass/fail criteria where appropriate.

6) Infrastructure requirements

I should like this document, initially, to be as complete as possible in terms of the possible tests to be performed. In actual production, and with experience, it will become clear which of the tests are actually necessary in terms of verifying the final production quality.

Despite the categorical tone, nothing is set in stone, everything is up for discussion.


2.Testing sequence

I divide the testing into component(essentially hybrids and detectors), sub-assembly (check on metrology), and module (final tests). In addition to this sequence there is a section defining tests to be performed after each transport of the module or hybrid, to ensure that no damage has occurred in transit.

I define and use the following terms:

Bare hybrid: hybrid with no components or connectors

Stuffed hybrid: hybrid with passive components and connectors

ASIC mounted hybrid: stuffed hybrid with ASICs mounted

Module: Finished product, fully mounted with detectors.

I have tried to define as full a set of tests as may be initially necessary; these tests may be reassessed after a preproduction run and may be omitted or only performed on a sample of components.

2.1 Component tests

2.1.1 Introduction

I treat the hybrid and detectors separately and assume that the finished pieces at the end of this stage are : Electrically tested hybrids with chips on;Tested detectors ;Inspected (tested?) additional mounting pieces, including baseboard.

2.1.2 Reception of parts

All parts are received and checked against an inventory; where appropriate, manufacturers information is entered in the database.
The pieces are visually inspected for obvious defects.
Some parts (which ones?) may be mechanically measured on a batch basis to ensure they are within tolerance.

2.1.3 Bare hybrid tests

1. The manufacturer shall manufacture the hybrids adhering to standard IPC-6013 'Qualification and Performance specification for flexible printed boards'. For this purpose, the hybrids are to be regarded as 'class 3' circuitry.

2. The isolation of the HV line shall be tested up to 600V

2.1.4 Stuffed hybrid tests

1. The stuffed hybrid shall undergo thermal cycling ten times from -20°C to 20°C and then retested for continuity.

2.1.5 ASIC mounted Hybrid tests

All temperatures are referred to the hybrid temperature sensor.

1. The hybrid is subject to a 'characterisation test' at the operating temperature.
2. The hybrids are cycled ten times from -20°C to 20°C while maintaining a constant check on the currents (this may be redundant)
3. The first batch of hybrids are subjected to a 100 hour burn-in at 20°C while checking the currents; subsequent batches may be subjected to shorter burn-in.
4. Full test vectors checking each chip are sent, and the reply read back and checked for conformity
5. A data run (detail
http://sroe.home.cern.ch/sroe/Electric.pdf) is performed on each hybrid at the end of the burn-in to ascertain the overall dynamic functionality and individual channel characteristics (gain, pedestal, noise) at the operating temperature.
 

 

2.1.6 Detector tests

1. IV characteristic up to 300 V

2.1.7 Fan-in tests

1. The fanins will be inspected optically for shorts

2. The fanins will be tested electrically

2.1.x other pieces...

 

2.2 Sub-assembly tests

1. Reception tests, as defined in 2.4
2. Leakage current of the glued detector assembly
3. Intermediate metrology, 113 points per module
, follow: http://hepwww.ph.man.ac.uk/groups/atlas/module/su2.ps
 

2.3 Module tests

1. Reception tests, as defined in section 2.4.
2. Detector IV
3. Detector I-time stability (in parallel with 6)
4. Cycle from +20 to -20 ten times, checking currents
5. Check metrology and dynamic deformation

6. Thermal image of an operating module at 20 degrees, measured on the hybrid.
7. 100 hour burn in at the operating temperature, checking currents
8. Data run at the operating temperature
9. Source or laser data run at operating temperature.

2.4 Tests after shipping of a hybrid or module

1. Visual inspection
2. Check supply currents
3. Supply clock, read back clock divide by two.
 


3. Batch tests

3.1 Hybrids

3.2 Detectors

Quantity

Initially 10%, reducing to 5% during production

Tests

1. Detector depletion voltage

2. Strip integrity

3. Leakage current stability

4. Irradiation testing

 

3.3 Diagnostic tests

Quantity

Only on batches showing problems

Tests


1. Interstrip capacitance

2. Polysilicon bias resistance and interstrip resistance

3. Full strip test

4. Metal series resistance

5. Coupling capacitance

6. Implant sheet resistance

7. Flatband voltage

 


4. Standard Testing Conditions

4.1 Chip tests on the hybrid or full module

4.1.1 Check of hybrid supply currents

Aim

Gross check of chip and hybrid functionality
 

Procedure

The currents should be checked, unless specified,  at room temperature with a current limited supply.
DACs should be at their nominal values. This requires the hybrid to be clocked, reset, then configuration and DAC commands to be sent.
The values are to be read 5 minutes after configuration to allow the chips to warm up.

Acceptance criteria

For the ABCD:
 
Voltage [V]  Nominal current  Acceptable range  Supply limit 
Vdd  4.0±0.1 

40 mA per slave

50mA per master 

±20%  600 mA 
Vcc  3.5±0.1  44 mA per chip  ±20%  700 mA 
 
 
 

4.1.2 ASIC mounted Hybrid temperature cycling

Aim

This test is intended to catch bad surface mount soldering and microcracks.

Procedure

The hybrids are cycled from -20°C to 20°C ten times while connected to their supply, temperature measured on the hybrid

A thermal image should be taken to demonstrate that each chip is well coupled to the hybrid.

Acceptable current behaviour over this range is yet to be ascertained.
 
 

4.1.3 Burn-in

Aim

Accelerated aging of the chips to catch infant mortality

Procedure

The hybrids are mounted into a test bench. The chips are initialised and then clocked (40MHz) and triggered at 100kHz for the duration of the test. The temperature on the hybrid is monitored, as are the currents. The hybrids are maintained at 20°C for 100 hours. Alarm conditions should be set on the temperature and currents, so that the power is cut if necessary. Data may be read during the burn-in.
 

4.1.4 Confirmation sequence

Aim

Gross check that each chip responds to a simple command

Procedure

see: http://sroe.home.cern.ch/sroe/Electric.pdf

Acceptance

Every chip responds as predicted
 

4.1.5 Characterisation sequence

Aim

Check that the chip responds to the full range of commands

Procedure

see:http://sroe.home.cern.ch/sroe/Electric.pdf

Acceptance

Every chip responds as predicted

4.1.6 Data run

Aim

Optimisation of chip parameters on a chip by chip basis (e.g. strobe delay, bias and shaper currents), measurement of the chip characteristics: gain, pedestal, noise

Procedure

see:http://sroe.home.cern.ch/sroe/Electric.pdf

Acceptance

Gains, pedestals and noise within acceptance criteria (being defined); total number of bad channels within acceptance.
 
 

4.2 Detector tests

Link for detector specification document (Maintained by Phil Allport)

Detailed testing procedures for all detectors, batch testing and irradiation testing are to be found in the QA documents maintained by Dave Robinson:

'ATLAS SCT Detector QA procedures'

'ATLAS SCT Detector Irradiation QA procedures'

'ATLAS Detector Qualification Tests'

 

 

4.4 Fan-in tests

4.x Other tests, metrology


5. Table of tests, variables stored and acceptance criteria

Follow database links on title page.

 

6. Infrastructure requirements

6.1 Basic requirements

It is assumed that the tests are carried out in a lab with access to standard electronics test equipment (oscilloscopes, multimeters etc.) In addition, a microscope with up to x80 magnification is assumed to be available for various visual inspections.

6.2 Assembled hybrid testing

Tests described in 2.1.3, and section 4.1.

Equipment

Environment chamber or test box, enabling temperature cycling from -20 to +50 deg C with humidity control (or nitrogen flushing) to prevent condensation.

Burn in and other tests are to be performed in parallel, so (at least!)two sets of the following are required:

6.3 Detector testing

Described in section 4.2; refer to linked documents for an exhaustive list.

Equipment

6.4 Module tests

Described in section 2.3

Equipment

6.5 Other component tests

Metrology....?