From: SMTP%"Antony.Carter@cern.ch" 17-MAR-1998 22:54:14.72 To: ATLAS-SCT@atlas-lb.cern.ch CC: Subj: UPDATE TO MODULES 1998 PROGRAMME THE MODULES 1998 PROGRAMME: UPDATE FROM THE MARCH SCT WEEK ____________________________________________________________ Following the project reviews during the March 1998 SCT Week, and the confirmed delay in availability of front end chips in sufficient quantity of the required performance, it was agreed by the Institute Board to reduce the target numbers of ELECTRICAL MODULES to be constructed in the period up to end-JULY/early-AUGUST. The new numbers are given in the table below, and these will require the MODULES construction programme to have access to numbers around 100 n-type and 80 p-type ABCD chips in the near future. For the post-August programme it is necessary to secure additional runs of chips with improved performance. In view of the reduced numbers of constructed modules for the near future could Cluster contacts please inform us of any modifications they wish to have made in item orders or delivery times. Best regards, Nobu and Tony. ____________________________________________________________________________ Appendix [B]: ELECTRICAL MODULE PRODUCTION FOR 1998 [last updated March 15th 1998] The general target numbers for module production given below were agreed at the SCT Institute Board on MARCH 13th 1998: _____________________________________________________________________________ MODULE TYPE: B-1 | B0 || F-2 | F-1 | F0 | _____________________________________________________________________________| |By end|May to |By end|Sept to||By end|May to |Aug to |By end | CLUSTER : |April |end July|August|end Dec||April |end July|end Dec|Dec | |________________________________________________________________| Japan | 1 | 1 | 4 | 4 || | | | | |______________________________||________________________________| USA | 1 | 1 | 2 | 2 || | | | | |______________________________||________________________________| Scdvian | - | 1 | 2 | 2 || | | | | |______________________________||________________________________| UK-B | 1 | 1 | 4 | 4 || | | | | |______________________________||________________________________| C-EU | | | | || 1 | 1 | 2 | 5 | |______________________________||________________________________| CERN/G/A | 2 | | | || 1 | 2 | 2 |up to 3,| | | | | || | | |depends | | | | | || | | |on prog.| | | | | || | | |status | |______________________________||________________________________| UK-V | | | | || 1 | 1or2 | 2 | 5 | ___________________________________________||________________________________| _