(Working draft) MODULES schedule Last update: 98/5/13 1) Parts availability (updated 98/5/13) Detector FEE Hybrid(unstuffed) Proto-2 --- Aug 98 Jul 98 Proto-1 NOV 98 Feb 99 Dec 98 Proto-0 SEP 99 Oct 99 Sep 99 Clearly, the FEE is in the critical path. With these dates in mind, the following is a working draft of the modules schedule. Please check and criticize. 2) Modules (Barrel & Forward) (updated 98/5/13) OCT 98 - Barrel module design frozen - TPG, Beryllia delivered - (b) Module-2 assembled and measured - (b) Module-2 irradiated - (b) MODULE-2 MULTI-MODULE TEST MAR 99 - (b) Module-2 fully evaluated OCT 98 - Forward module design frozen - TPG, Beryllia delivered - (f) Module-2 assembled and measured - (f) Module-2 irradiated - (f) MODULE-2 MULTI-MODULE TEST MAR 99 - (f) Module-2 fully evaluated APR 99 - Barrel & Forward Design Review - Assembly tooling REVIEW - Test and QA procedure REVIEW - (b) Module-1 assembled - (b) Module-1 measured (geometry, thermal, electrical) - (b) Module-1 irradiated - (b) Module-1 measured (geometry, thermal, electrical) - (b) MODULE-1 MULTI-MODULE TEST AUG 99 - (b) Module-1 fully evaluated - (f) Module-1 assembled - (f) Module-1 measured (geometry, thermal, electrical) - (f) Module-1 irradiated - (f) Module-1 measured (geometry, thermal, electrical) - (f) MODULE-1 MULTI-MODULE TEST AUG 99 - (f) Module-1 fully evaluated SEP 99 - Module Design Review - Specification for procurement OCT 99 - PRR - Call for tender - Contract placed - Module0 ready for tests - MODULE0 MULTI-MODULE TEST MAR 00 - Module0 tests complete - Module assembly QA & test procedure complete - Module assembly tooling available APR 00 - Start of module production NOV 00 - 10% of module production APR 01 - 25% of module production AUG 02 - Module production complete